Construction Update: Intersection of South St, S. Titus & Fair St.

Work Zone

Construction Update: Intersection of South St, S. Titus & Fair St.


PROJECT NAME & LOCATION: Storm pipe replacement, intersection of South St, S. Titus & Fair St.

PROJECT START DATE: Monday, February 5, 2024

PROJECT DESCRIPTION AND GOAL: - Replace 2 existing storm pipes, repair connecting 3 catch basins and adjoining catch basin repairs.

LOCAL IMPACTS: The indicated road will be temporarily closed during Storm Pipe replacement from February 5, 2024, through February 21, 2024, between the hours of 7am – 3:30pm.
Sidewalks will not be affected by this construction.
Emergency vehicles and local residents will have access to driveways though-out the duration of the project. Some parking near the work zone will be utilized for City vehicles and will be posted. Some delays should be expected during work. The street will remain closed for the duration of the project.

RECOMMENDED DETOURS
Residents on Fair St (100 Block) & 500 Block of S. Titus will need to use S. Meadow St.
Residents on Fair St (200 Block) can utilize Wood St.
South St. at Meadow will not be closed and can be accessed by the 200 Block of Fair St.
Those traveling East on S. Titus will utilize Wood St to S. Plain St. then turn right on S. Titus St.
Those traveling West on S. Titus St. will turn left on S. Plain St and right on Wood St.

ESTIMATED TIME FRAME: 16 days

SCHEDULED COMPLETION DATE: Wednesday, February 21, 2024

PLEASE NOTE: Construction, by nature, is subject to constant change, inclement weather, and unexpected findings.

For additional information contact: Laurie Ervay (607) 272-1718 ext. 4224; lervay@cityofithaca.org