Construction Update- Spencer Road Milling and Paving

Construction Update- Spencer Road Mill & Pave

PROJECT START DATE:  August 2, 2019

PROJECT NAME:  Spencer Road  - Mill and Pave

PROJECT LOCATION:  Spencer Road  - From the Traffic Circle to Stone Quarry Road

PROJECT DESCRIPTION AND GOAL:  Mill existing road surface and prepare for asphalt overlay.

LOCAL IMPACTS:  Traffic will be controlled by flaggers for the duration of the milling process. Spencer Road will be closed for paving after South Aurora Street has been re-opened to accommodate traffic detour (estimated date August 15, 2019).

RECOMMENDED DETOURS IN PLACE:  Traffic controlled by flaggers for the duration of the milling of the road.  South Aurora Street will serve as a detour route while Spencer Road is re-paved.  

ESTIMATED COMPLETION DATE:  August 30, 2019

For additional questions and concerns, please contact the City of Ithaca Streets & Facilities Department at (607) 272-1718