News Flash

City of Ithaca News

Posted on: September 12, 2023

Construction Update: 100 Block Wood St. & 400 Block S Geneva St

work_zone

Construction Update: 100 Block Wood St. & 400 Block S Geneva St

PROJECT NAME & LOCATION: Road Pavement Repair; 100 Block Wood St. & 400 Block S Geneva St. (from South Albany St. to South Titus Ave.) 

PROJECT START DATE: Thursday, September 14, 2023 

PROJECT DESCRIPTION:  - Full depth asphalt pavement repair at spot locations with some curbing installation and replacement of a storm sewer pipe.   

PROJECT GOAL: Pavement condition rehabilitation   

LOCAL IMPACTS:  Beginning on Thursday, September 14th, the 100 block of Wood St. and the 400 block of S. Geneva St. will be closed to thru traffic with no parking on the street between S. Albany St. and S Titus Ave. Vehicular access within the road closure will be provided for local residents only for entering and exiting driveways and as construction operation allows; however, there will be frequent blockages of the street and driveways,  therefore the city recommends parking elsewhere for the duration of the project.  

RECOMMENDED DETOURS IN PLACE:  No detours will be put in place. 

ESTIMATED TIMEFRAME:  1 week.  

SCHEDULED COMPLETION DATE:  Friday, September 22, 2023. 

PLEASE NOTE:  Construction, by nature, is subject to constant change, inclement weather, and unexpected findings.

FOR ADDITIONAL INFORMATION CONTACT: Alfonso Reyes Vasquez, Construction Engineer, DPW Streets & Facilities Division (607)272-1718 ext. 4223; areyes@cityofithaca.org 

Facebook Twitter Email