Construction Update: Oak Avenue Sewer Installation
PROJECT LOCATION: Oak Avenue between College Ave and Summit Street
PROJECT DESCRIPTION: New Sewer Installation
PROJECT START DATE & TIME: 7:00 AM Tuesday December 20th
SCHEDULED COMPLETION DATE: 3:30 PM Friday January 20th
INTERRUPTIONS TO WATER SERVICE: None.
LOCAL IMPACTS: Oak Avenue will be closed between College Avenue and Summit Street, except for residential access.
RECOMMENDED DETOUR: Dryden Road may be used to bypass the construction area.
For additional information contact: Nick Thomas, James Lauper, or Ethan Bodnaruk, DPW, Water & Sewer Division (607) 272-1717