Construction Update- 300 Block Center Street
PROJECT NAME & LOCATION: 8” Water Line Upgrade 300 Block of center Street between N. Titus & S. Plain Street
PROJECT GOAL & DESCRIPTION: Upgrade water line & strengthen water main service
PROJECT START DATE & TIME: Monday April 5, 2021 7:00 AM
SCHEDULED PHASE COMPLETION DATES: Friday April 30, 2021 by 3:30pm
LOCAL IMPACTS: Road will be closed to thru traffic, will maintain emergency and local access
For additional information contact: Don Corwin, Matt Sledjeski or Scott Gibson with DPW, Water & Sewer Division (607) 272-1717