Construction Update: Gas work along Plain St., Wood St., Albany St., and Park St.

construction-Gas work

Construction Update: Gas work along Plain St., Wood St., Albany St., and Park St.

PROJECT LOCATION: Southside neighborhood area along Plain St., Wood St., Albany St., and Park St.

PROJECT START DATE: Tuesday, April 21, 2020

PROJECT DESCRIPTION: DDS Companies will install new gas mains (and service connections later) in the project area.

LOCAL IMPACTS: Expect one lane traffic conditions during work hours. Flaggers will direct traffic. Sidewalk detours may occur. 

PROJECT COMPLETION: This preliminary gas main work is expected to take about 4 to 6 weeks.

DETOURS IN PLACE: Detours are not expected for motorists.

PARKING RESTRICTIONS: Construction operations and material storage will occupy some parking spaces on the affected streets.

PLEASE NOTE: Due to COVID-19 precautions, just the gas main work in the street area is being conducted at this time. Individual gas services to residences will be conducted later to minimize risks. This preliminary gas main work is expected to take about 4 to 6 weeks. 

For questions, please contact Kent Johnson, City of Ithaca Assistant Transportation Engineer, at kjohnson@cityofithaca.org.