Construction Update - Water & Sewer Work - 800 Block South Aurora Street

PROJECT NAME: Water & Sanitary Sewer Main Extension Street Crossing

 PROJECT LOCATION: 800 Block of South Aurora St

WORK DESCRIPTION:  Extend new section of water and sanitary sewer main across South Aurora St. Utility trench reconstruction to follow.  

 PROJECT START DATE: Monday, July 8th, 7:00 AM

 SCHEDULED COMPLETION DATE: Friday, July 19th, 3:30 PM

LOCAL IMPACTS: The “South Aurora Street Sidewalk Extension” project is still in progress between Hillview Pl and Grandview Ave.

An additional section of South Aurora St between Grandview Ave and Coddington Rd will be closed at all times during the utility work. Local and emergency access will be maintained.

RECOMMENDED DETOURS: Northbound traffic should turn right on Coddington Rd, left on Hudson Pl, left on Hudson St, and follow posted detour signs to return to South Aurora St. Southbound traffic should follow posted detour signs to turn left on Hudson St, right on Hudson Pl, and right on Coddington Rd to return to South Aurora St.

INTERRUPTIONS TO WATER SERVICE: During connection of the new main, water service may be interrupted briefly for customers in the 700 and 800 Blocks of South Aurora St. Affected properties will be given advance notice of the shutdown in person and with a door hanger notice.

Questions or concerns about this project can be forwarded to the Water & Sewer Division at (607) 272-1717.