Construction Update- 600 Block E State Street/ MLK Jr Blvd

Construction Update- 600 Block E State Street/ MLK Jr Blvd

PROJECT NAME: Preparation for sewer service replacement

PROJECT LOCATION: 600 Block E State St / MLK Jr Blvd

WORK DESCRIPTION:  Saw-cut asphalt pavement in preparation for replacing several sanitary sewer services.  

PROJECT START DATE: Wednesday, April 17th, 7:00 AM

SCHEDULED COMPLETION DATE: Friday, April 19th, 3:30 PM

LOCAL IMPACTS: The westbound travel lane will be closed in the vicinity of the work. Flaggers will direct traffic around the work zone. The work site will shift as crews move from one service to the next.

RECOMMENDED DETOURS: No posted detour

For additional information contact: Don Corwin, Erik Whitney, or Matt Sledjeski with DPW, Water & Sewer Division (607) 272- 1717